Legislation Details

File #: 26-5538    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 4/7/2026 In control: Town Council Meeting
On agenda: 4/27/2026 Final action:
Title: Request Authorization for Additional Contract Expenditure for the Nutley Street Culvert Construction Contract, IFB 25-02, with FLB Contractors, Inc. (5 mins)
Attachments: 1. 1. Specifications - Fairfax County FRP Casing Pipe Spec, 2. 2. Cost Proposal - 66-Inch FRP Casing Pipe-Nutley Culvert Replacement-FLB, 3. 3. Vienna_County_Cost Reimbursement Letter, 4. 4. REGULATORY Requirements for 26-5538- Agenda Items Rev - June 14, 2024

Subject:

Title

Request Authorization for Additional Contract Expenditure for the Nutley Street Culvert Construction Contract, IFB 25-02, with FLB Contractors, Inc. (5 mins)

Body

DATE(S) OF PRIOR COUNCIL CONSIDERATION OF THIS ISSUE:

Nov. 18, 2013 - Approval of original design contract

March 7, 2016 - Approval of funds for additional hydraulic analysis

April 8, 2024 - Approval of updated design contract for the Nutley Marshall Culvert Replacement project using ARPA funding

Oct. 28, 2024 - Approval to award IFB 25-02 to FLB Contractors, LLC. for construction of the Nutley Street Culvert

EXPLANATION AND SUMMARY:

Request:

The Department of Public Works requests Town Council approval to award a change order for the Nutley Street culvert construction contract, IFB 25-02, in the amount of $253,003.50 and increase the contract value from $1,599,218.05 to $1,852,221.55 plus 25% contingency reserve for a total authorization of $2,315,277.

This $255,003.50 change order is fully funded by Fairfax County in support of the Accotink Gravity Sewer project that will be constructed in this same location at a future date.  The purpose of the change order is to install a 66-inch casing pipe under the new culvert to accommodate Fairfax County’s future sewer line.  Authorizing this additional work will benefit the Town of Vienna to reduce the traffic impacts from future Fairfax County construction on Nutley Street, SW, after the Nutley culvert is completed.

Discussion:

The ongoing Nutley Street Culvert project replaces the existing triple barrel, 36-inch diameter culvert that crosses under Nutley Street with a larger proposed box culvert.  Fairfax County's future Accotink Gravity Sewer project, which involves a 66" sanitary sewer pipe, will cross underneath the new culvert. 

Fairfax County has requested that the Town of Vienna's contractor install a casing pipe below the culvert.  Fairfax County proposed a change order be issued by the Town of Vienna for $253,003.50 and be reimbursed by Fairfax County for the full amount within 30 days of completion of the work.

Town staff have reviewed and signed a letter of agreement between Fairfax County and Town of Vienna, which has substantial benefits for the Town of Vienna and Fairfax County.  Installing this casing pipe will reduce the construction traffic impacts on Nutley Street during the future Accotink Gravity Sewer project.  Coordination between the Town of Vienna and Fairfax County will eliminate potentially redundant construction work and excavation on Nutley Street.

Next Steps: FLB Contractors, Inc. will complete the installation of the casing pipe, and the Town of Vienna will be reimbursed by Fairfax County for the full $253,003.50 cost of the change order.

Expected Completion Time Frame: Construction of casing pipe to be completed by May 2026

Strategic Plan Initiative: Vienna is an environmentally sustainable community

Departmental Recommendation:  Recommend approval.

Finance Recommendation:  Recommend approval.

Purchasing Recommendation: Recommend approval. 

Town Attorney Recommendation:  The Town Council may approve the proposed contract change order, with reimbursement by Fairfax County, in its discretion.

Town Manager's Recommendation:  I recommend the Town Council approve a Fairfax County funded change order for the Nutley Street Culvert Construction contract, as presented.

Cost and Financing: $253,003.50

Account Number: Project Acct: 130-551-9506-55911-48803

Prior Funding Approval: Oct. 28, 2024

Decision Needed by This date: April 27, 2026

PROPOSED/SUGGESTED MOTION

Recommended Action

"I move to approve a Fairfax County funded change order for the Nutley Street Culvert Construction Contract, IFB 25-02, in the amount of $253,003.50 and increase the contract value to $1,852,221.55 plus 25% contingency reserve for a total authorization of $2,315,277 as described in this report.

Or

Other action deemed necessary by Council.