Title: Award IFB 22-06 for the Provision and Installation of Water Mains - As Needed to Crown Construction Service, Inc. and approval for spending $1,000,000 for water main improvements within the Town's service area
Attachments: 1. 1. Completed Water and Sewer Capital Projects from 2020 Bond (FY 20 - Current)_2022-01-12, 2. 2. IFB 22-06 FINAL, 3. 3. IFB 22-06 Summary Report and Bid Tab, 4. 4. Proposed Water and Sewer Capital Projects Jan 2022, 5. 5. Regulatory Requirements for Agenda Items Rev 011222
Subject:
Title
Award IFB 22-06 for the Provision and Installation of Water Mains - As Needed to Crown Construction Service, Inc. and approval for spending $1,000,000 for water main improvements within the Town's service area
Body

EXPLANATION AND SUMMARY:

On Nov. 17, 2021, the Town's purchasing agent opened bids for IFB 22-06 Provision and Installation of Water Mains - As Needed, with six firms responding. Crown Construction Service, Inc. submitted the low bid of $2,271,937 and has been deemed the lowest responsive and responsible bidder. This is an on-call unit price contract and therefore can award an amount less than the total bid.

At this time, in conjunction with the contract approval, the Department of Public Works requests approval for spending $1,000,000 to utilize IFB 22-06 Provision and Installation of Water Mains - As Needed for improvements throughout the Town's service area. Improvements will consist of new water meter installation, repairs to aging infrastructure, and provisions to increase the Town's water system functionality. Improvements will be prioritized based on water main break data and in coordination with concurrent Town projects. Specific project locations, selected from those on the attached list, will be posted to the Town website, and all impacted customers will receive notification with additional information and points of contact prior to the start of construction. Funds will come from the 2020 CIP Bond. Previous projects completed using 2020 CIP Bond funding are also included in the attached list.

Strategic Plan Initiative: Vienna is an environmentally sustainable community.

Departmental Recommendation: Award IFB 22-06 for the Provision and Installation of Water Mains - As Needed to Crown Construction Service, Inc. and approve spending in the amount of $1,000,000 for water main improvements within the Town's service area.
Finance Recommendation:
Purchasing Recommendation: Recommend approval