BACKGROUND SUMMARY:

On 9/16/2019 Town Council approved the VDOT Revenue Sharing funding application for the Church St and East St Roundabout.

 

On 10/23/23 Town Council approved the 2024 Capital Improvement Plan that included this project.

 

On 5/6/2024 Town Council approved DPW to award a design contract to Rummel, Klepper & Kahl, LLP (RKK) in the amount of $379,129.00 for the Church St and East St NE Roundabout project.

 

OVERVIEW:

The initial study and concept design have been completed.  This is a brief Work Session update on the subject project.  An overview of roundabouts, the concept design, and the way forward before proceeding will be presented.

SUMMARY/STAFF IMPRESSIONS:

 

RECOMMENDATION:

Recommended Action

None, for informational purposes and discussion.