File #: 16-099    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 4/4/2016 In control: Town Council Meeting
On agenda: 4/18/2016 Final action:
Title: Increase funds to the Vienna Community Center renovation and expansion project

Subject:

Title

Increase funds to the Vienna Community Center renovation and expansion project

Body

EXPLANATION AND SUMMARY

 

The proposed $287,200 expenditure will be used to address design and construction costs necessary to continued progress on the Vienna Community Center renovation and expansion project. These costs have been accounted for in funds approved during the February 22, 2016 Town Council Meeting. 

 

Departmental Recommendation:  Recommend approval.

 

Finance Recommendation:  Recommend approval.

 

Purchasing Recommendation:  N/A

 

Town Attorney Recommendation: Town Council may approve the proposed contract modification and expenditure of funds in its discretion.

 

Town Manager's Recommendation:  I recommend the Town Council increase the Vienna Community Center construction contract with Keller Brothers as presented.

 

Cost and Financing:  $287,200

Account Number:  300-00-000-39425-48803

Decision Needed by This date:  N/A

 

PROPOSED/SUGGESTED MOTION

Recommended Action

"I move to increase the Vienna Community Center construction contract with Keller Brothers, Inc. in an amount not to exceed $266,577 for the Vienna Community Center project, IFB 16-04, account listed above."

And

“I further move to approve payment to Robert E. Lee Electric in an amount not to exceed $20,623 for the Vienna Community Center project, IFB 16-04, account listed above."

Or

Other action deemed necessary by Council.