File #: 16-339    Version: 1 Name:
Type: Action Item Status: Passed
File created: 1/18/2017 In control: Town Council Meeting
On agenda: 1/30/2017 Final action: 1/30/2017
Title: Request for approval of a Modification and Addendum to Contract IFB 16-04, construction contract with Keller Brothers Inc. for the Vienna Community Center renovation and expansion related to the substantial completion date and associated general conditions payment claims.
Attachments: 1. MODIFICATION AND ADDENDUM TO CONTRACT IFB 16 04 SDB 01 26 2017 wJM Edits wSDB Edits Ver 4
Subject:
Title
Request for approval of a Modification and Addendum to Contract IFB 16-04, construction contract with Keller Brothers Inc. for the Vienna Community Center renovation and expansion related to the substantial completion date and associated general conditions payment claims.
Body
EXPLANATION AND SUMMARY:

The proposed Modification and Addendum covers the delay claims associated with approved project change orders. The proposed Modification and Addendum will set a new "substantial completion date" as well as approve general condition payments to the Contractor that would be due under the contract for certain delays in the project. Under the terms of the proposed Addendum, the new Project Substantial Completion date would be August 11, 2017.

The Town Manager, the Town's Scheduling Consultant, the Town Attorney, and staff have participated with the Contractor in the review, analysis and discussion of the proposed contract modification and general condition payments associated with project delays and reached a proposed net amount of additional days and compensable general condition payments to the Contractor. Any delays associated with the Contractor and/or not compensable under the terms and conditions of the IFB have been accounted for and credited.

This amount is covered in the contingency already approved by Council in July, 2016.

Departmental Recommendation: Recommend approval.

Finance Recommendation: Recommend approval.

Purchasing Recommendation: N/A

Town Attorney Recommendation: The Town Attorney, with the assistance of the Town's outside scheduling consultant, recommends the approval of the proposed Modification and Addendum to Contract IFB 1604.

Town Manager's Recommendation: I recommend the Town Council approve the proposed Modification and Addendum as presented.

Cost and Financing: $113,226
Account Number: 300-000-0000-39425-48803
Decision Needed by This date: January 30, 2017