File #: 24-4363    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 3/18/2024 In control: Town Council Meeting
On agenda: 4/8/2024 Final action:
Title: 9:00 p.m. - 9:30 p.m. Request to Award a Design Contract to Whitman, Requardt & Associates, LLP, for Nutley Street Culvert Replacement.
Attachments: 1. 1. Nutley Street Culvert - WRA Finalization Proposal - January 23, 2024, 2. 2. Citizen Meeting Notice - Nutley Street Culvert Replacement - March 25, 2024, 3. 3. Nutley Drainage Project Addresses - April 08, 2024, 4. 4. Regulatory Requirements for 24-4363 - Agenda Items Rev - March 18, 2024
Subject:
Title
9:00 p.m. - 9:30 p.m. Request to Award a Design Contract to Whitman, Requardt & Associates, LLP, for Nutley Street Culvert Replacement.

Body
DATE(S) OF PRIOR COUNCIL CONSIDERATION OF THIS ISSUE:
Nov. 18, 2013 - Approval of original design contract
March 7, 2016 - Approval of funds for additional hydraulic analysis
Sept. 19, 2017 - 2018 CIP
Feb. 7, 2020 - 2020 CIP
Jan. 24, 2022 - 2022 CIP
Moved to ARPA, 5 work sessions and 4 Council action items regarding ARPA in 2022 and 2023

EXPLANATION AND SUMMARY:

The Department of Public Works (DPW) requests Town Council approval to proceed with a contract in the amount of $230,936.50 with Whitman, Requardt & Associates, LLP to provide engineering services for survey, easement plats, utility test holes, and design utilizing the on call Civil Engineering contract RFP 23-37.

The Nutley Street storm water culvert system includes an existing triple barrel, 36-inch diameter culvert that crosses under Nutley Street near the intersection with Virginia Center Boulevard and Marshall Street. The existing culvert is undersized, and this project will mitigate flooding issues for surrounding homes. The proposed design services will replace the existing culvert with twin 10-foot by 6-foot culverts with an updated hydraulic and hydrologic analysis, traffic control, and technical specifications.

Next Steps: Complete the design phase and request approval for the construction phase at a subsequent Town Council meeting.

Expected Completion Time Frame: Complete design by August 2024 and award construction in the Fall of 2024.

Strategic Plan Initiative: Vienna is an environmentally sustainable community.

Departmental Recommendation: Recommend approval.

Finance Recommendation: Recommend approval.

Purchasing Recommendation: Recommend approval.

Town Attorney Recommendation: The Town has an engineering services contract with Whitman, Requardt & Associates, LLP and the Town Council may approve the appropriation of f...

Click here for full text